Technical Specifications

  • Positioning of the edge stop beam
  • Fixing of the gutter
  • Torch down a vapour barrier to the roof top made of  bitumen membrane of at least 3 mm thick
  • Again using a hot torch, immediately lay down STIFERITE’s Class B panels on the top surface of the previous membrane
    (alternative: STIFERITE’s Class SSTIFERITE's GT3 – GT4 – GT5)
  • Torch down  of bitumen membrane with slate chips finish of 4,5 kg/m2 to the top surface of  Class B panel
  • Followed by the installation of the first rows, or as many as necessary (depending on the amount of pitch and wind conditions), of tiles using polyurethane foam

Instructions and Guidelines
An adequate thermal insulation and waterproofing package not only assures thermal ambient comfort, but also long term durability of the terracotta soffit inside the roof.

The waterproofing membrane protects the roof prior to the installation of the tiles and in case of accidental brakes, it assures the necessary waterproofing.

The use of the vapour barrier is indispensable for the correct functionality of the system

Also see: the installation procedure

The tables indicate the suggested thickness of Stiferite’s panels based on

  • Climate Zones
  • Current legislative set limits of thermal transmittance
  • And the following composition of the structure:

 

Suggested thickness
STIFERITE Class B - Class S
Climate
Zone

DLgs 311/06

TAX deduction MD 65%
DM 26/10/2010

A 70 mm 80 mm
B 70 mm 80 mm
C 70 mm 80 mm
D 80 mm 100 mm
E 80 mm 100 mm
F 80 mm 100 mm

 

Suggested thickness
STIFERITE GT3 - GT4 - GT5
Climate
Zone

DLgs 311/06

TAX deduction MD 65%
DM 26/10/2010

A 60 mm 70 mm
B 60 mm 70 mm
C 60 mm 70 mm
D 70 mm 90 mm
E 70 mm 90 mm
F 80 mm 100 mm

 

Note: For different composition of structures or material, we suggest using the calculation program available online (see: Thermal transmittance and verifications of condensation with Glaser method)

 

 